30 Questions • 60 Minutes • Quantitative Aptitude Mock Test in Hindi and English
• Given: Time taken by A days, B days.
• Basic Method (Solution):
Step 1: Total work units.
Step 2: Efficiency of A units/day. Efficiency of B unit/day.
Step 3: Total efficiency units/day.
Step 4: Time taken days.
• Shortcut Method: When A and B work together, time taken . Here, days.
• Final Answer: 8
• Given: , , days.
• Basic Method (Solution):
Step 1: Total work units.
Step 2: Efficiency: , , .
Step 3: Total efficiency per day units.
Step 4: Total time days.
• Shortcut Method: LCM total-work method is the fastest shortcut here. Mental math: . Sum of efficiencies . Answer .
• Final Answer: 4
• Given: days, days.
• Basic Method (Solution):
Step 1: Total work units.
Step 2: efficiency units/day.
Step 3: 's efficiency units/day.
Step 4: 's efficiency unit/day.
Step 5: Time for B days.
• Shortcut Method: Formula for remaining person: Time days.
• Final Answer: 24
• Given: , , ,
• Basic Method (Solution):
Step 1: Use MDH formula .
Step 2: .
Step 3: .
Step 4: days.
• Shortcut Method: Work is constant. Ratio of Men . Time is inversely proportional to Men, so Time ratio . If 5 units days, 1 unit days, so 3 units days.
• Final Answer: 12
• Given: .
• Basic Method (Solution):
Step 1: Use the full MDH formula:
Step 2:
Step 3: Simplify left side: .
Step 4: Simplify right side: .
Step 5: .
• Shortcut Method: Directly write . Cancel out zeros and simplify: .
• Final Answer: 24
• Given: A's efficiency = B's efficiency. Together time days.
• Basic Method (Solution):
Step 1: Let B's efficiency unit/day. Then A's efficiency units/day.
Step 2: Total efficiency units/day.
Step 3: Total work units.
Step 4: Time taken by A alone days.
• Shortcut Method: Ratio of efficiency . Total parts . Work . A's time days.
• Final Answer: 21
• Given: days, days, Total wage .
• Basic Method (Solution):
Step 1: Wages are distributed in the ratio of their efficiencies (work done).
Step 2: Total work .
Step 3: A's efficiency . B's efficiency .
Step 4: Ratio of wages . Total parts .
Step 5: A's share .
• Shortcut Method: Ratio of efficiencies is inverse of ratio of time taken. Time ratio . Efficiency ratio . A's share .
• Final Answer: ₹3000
• Given: A does work in days. B does work in days.
• Basic Method (Solution):
Step 1: Time taken by A to complete full work days.
Step 2: Time taken by B to complete full work days.
Step 3: Total work units.
Step 4: A's efficiency , B's efficiency . Total .
Step 5: Time taken together days.
• Shortcut Method: Full days . Use product/sum formula: days.
• Final Answer: 6 days
• Given: A fills in 20 hrs, B empties in 30 hrs.
• Basic Method (Solution):
Step 1: Total capacity of tank units.
Step 2: Efficiency of A units/hr.
Step 3: Efficiency of B units/hr.
Step 4: Net efficiency unit/hr.
Step 5: Time taken hours.
• Shortcut Method: When one fills () and one empties (), Net Time hours.
• Final Answer: 60
• Given: , . They work together for 4 days. Then A leaves.
• Basic Method (Solution):
Step 1: Total work units.
Step 2: Efficiencies: , . Total .
Step 3: Work done in 4 days units.
Step 4: Remaining work units.
Step 5: Time taken by B for remaining work days.
• Shortcut Method: Mentally calculate total work 60. In 4 days, they do . Left is 40. B's speed is 2. So days directly on paper.
• Final Answer: 20
+ 20 more questions inside...